2.3. Engineering Work Progress (contd.
)
Activity Name D Start Finish Planned % Actual %
Waterproofing Works Subcontractor
WP - Substructure
Submission of PQ - Substructure
14 19-Jun-25 05-Jul-25 43% 0%
waterproofing Subcon
Review & Approval of PQ - Substructure
14 19-Jun-25 05-Jul-25 43% 0%
waterproofing Subcon
Blockwork Supplier
Submission of PQ - Blockwork Supplier 14 19-Jun-25 05-Jul-25 43% 43%
Review & Approval of PQ - Blockwork
14 19-Jun-25 05-Jul-25 43% 43%
Supplier
Lift Subcontractor
Submission of PQ - Lift Subcon 21 03-Jun-25 30-Jun-25 100% 0%
Review & Approval of PQ - Lift Subcon 21 03-Jun-25 30-Jun-25 100% 0%
MEP SUBCONTRACTOR
Submission of PQ - MEP Subcon 14 17-May-25 02-Jun-25 100% 100%
Review & Approval of PQ - MEP Subcon 14 17-May-25 02-Jun-25 100% 0%
Electrical Materials
Sleeves, conduits & GI boxes
Submission of PQ & Material - Sleeves,
10 03-Jun-25 16-Jun-25 100% 0%
conduits & GI boxes
Review & Approval of Material - Sleeves,
14 03-Jun-25 20-Jun-25 100% 0%
conduits & GI boxes
Cables & wires
Submission of PQ & Material - Wires 10 17-Jun-25 28-Jun-25 80% 0%
Review & Approval of PQ & Material - Wires 14 17-Jun-25 03-Jul-25 57% 0%
Submission of PQ & Material - Cables 10 17-Jun-25 28-Jun-25 80% 0%
Review & Approval of PQ & Material - Cables 14 17-Jun-25 03-Jul-25 57% 0%
Water supply & Drainage Materials
Underground drainage pipes
Submission of PQ & Material - Underground
10 03-Jun-25 16-Jun-25 100% 0%
Drainage Pipe
Review & Approval of PQ & Material -
14 03-Jun-25 20-Jun-25 100% 0%
Underground Drainage Pipe
Underground Water Supply Pipes
Submission of PQ & Material - Underground
10 03-Jun-25 16-Jun-25 100% 0%
water supply Pipe
Review & Approval of PQ & Material -
14 03-Jun-25 20-Jun-25 100% 0%
Underground water supply Pipe
Above ground drainage pipes 14 17-Jun-25 03-Jul-25 57% 0%
Submission of PQ & Material - Above ground
10 17-Jun-25 28-Jun-25 80% 0%
Drainage Pipe
Review & Approval of PQ & Material - Above
14 17-Jun-25 03-Jul-25 57% 0%
ground Drainage Pipe
Page 9 of 19 Weekly Report # 001