01
Telecommunication
Tower Construction
Weekly Update
13/06/2025
Weekly Progress Report on Multiple Sites: LG2126, EN0833, ED1039, RV0727,
and ED1037
02
Site Locations
The construction update cover
the following Site:
1. LG2126,
2. EN0833,
3. ED1039,
4. RV0727, and
5. ED1037.
Current Status of Each Site
Currently,
A. LG2126: is progressing with the completion of foundation base and Column, Retaining wall, Rigging,
and painting of the tower. Ongoing at the site is the Guard House Construction, site levelling, erection of
pallisade etc.
B. EN0833: Through with the Excavation, foundation base rebar, foundation column rebar ongoing.
C. ED1039: Pile foundation at the site completed excavation for the retaining wall and pile cap is ongoing.
D. RV0727: As built Drawing has been prepared, remain the final cleaning, bulglary iin GH, retaining wall
dressing and razor wire installation.
E. ED1037: at the stage of handing over & commisioning. As-built drawing has been prepared, awaiting the
form H1-H7s.
LG2126 Picture Update
Current Status of Construction in LG2126
Total
Progress
8 % Construction Phase Distribution
0
On
Schedule 15 30
Yes 5
Remaining 50
Progress
2 % Site Preparation and Foundation Tower Erection
0
Safety Testing and Commission Equipment Installation
EN0833 Picture Update
Current Status of Construction in EN0833
Total
Progress
2 % Construction Phase Distribution
7
On
Schedule 15 30
No 5
Remaining 50
Progress
7 % Site Preparation and Foundation Tower Erection
3
Safety Testing and Commission Equipment Installation
ED1039 Picture Update
Current Status of Construction in ED1039
Total
Progress
2 % Construction Phase Distribution
7
On
Schedule 15 30
Yes 5
Remaining 50
Progress
7 % Site Preparation and Foundation Tower Erection
3
Safety Testing and Commission Equipment Installation
Current Status of Construction in RV0727
Total
Progress
9 % Construction Phase Distribution
7
On
Schedule 15 30
Yes 5
Remaining 50
Progress
0 % Site Preparation and Foundation Tower Erection
3
Safety Testing and Commission Equipment Installation
ED1037 Picture Update
Current Status of Construction in ED1037
Total
Progress
9 % Construction Phase Distribution
9
On
Schedule 15 30
Yes 5
Remaining 50
Progress
1 % Site Preparation and Foundation Tower Erection
Testing and Commission Equipment Installation
Safety
Challenges Encountered
• Unforeseen Community/security issues for RV0727
• Delay in provision of finance for LG2126 caused a serious delay
and the management has taken care of that.
• Unforeseen community issue/payment where our Piler equipment
were seized caused a serious delay for our site.
• Modification of Drawing for EN0833 took almost a week for
changes and approval.
• The ongoing weather-related (Raining season) delays LG2126
works sometimes.
Next Steps
As we move forward, prioritizing the
acceleration of assembly at LG2126
and speedup work on EN0833 is
crucial to keep the project on
schedule. This will involve
deploying additional labor resources
to streamline processes for LG2126,
EN0833 and ED1039 by the vendor.
Timeline Updates
This week’s timeline updates highlight that
• LG2126 is not progressing with the anticipated time.
• EN0833 is behind the planned scheduled.
• ED1039 is not progressing as expected.
• RV0727 and ED1037 is within the final stage of handing over
Conclusions
For the last 1 week most of our site has experience
different challenges which has slowed the work
progress and the management is working tirelessly to
avoid such problem in the future.
Thank you!